Neighbour refusing access for building work: what you can do

Need a surveyor fast?
1,920 listings across England and Wales, nearest first.

If your neighbour is refusing access for building work, what you can do depends on the kind of work. For work covered by a party wall notice, section 8 of the Party Wall etc. Act 1996 gives your builders and surveyors a right to enter on 14 days' notice. For essential repairs to your own property, you can ask the county court for an order under the Access to Neighbouring Land Act 1992. For anything else, including most scaffolding for new work, you need your neighbour's agreement, usually in a written licence.

Need a surveyor fast?
1,920 listings across England and Wales, nearest first.

Three routes compared

Party Wall Act, section 8 Access to Neighbouring Land Act 1992 Negotiated licence
What it covers Entry needed to carry out work under the Party Wall Act (s.8(1)) Works "reasonably necessary" to preserve your own land or building (s.1(2)) Anything both owners agree
Typical uses Cutting in beams, underpinning, making good the neighbour's side, a surveyor's inspection Repointing, roof or gutter repairs, clearing a drain, cutting back a dangerous tree Scaffolding for an extension, crane oversail, storing materials, access for a new build
Needs court? No Yes, an order from the county court (s.7(2)) No
Notice At least 14 days, or what's reasonably practicable in an emergency (s.8(3)-(4)) No fixed notice period in the Act; the court sets conditions Whatever you agree
Payment to neighbour Compensation for loss or damage (s.7(2)); no fee for entry Compensation for damage and serious inconvenience; no payment for the right of entry where the land is residential (s.2(5), s.2(7)) Negotiated. No statute sets a fee
If refused Refusing or obstructing entry can be an offence (s.16), and forced entry is allowed only with a police officer present (s.8(2)) The court decides; it can refuse if the hardship to your neighbour would be unreasonable (s.1(3)) You can't insist. Consider changing the method of work
Speed 14 days Weeks to months, plus legal costs As fast as you can agree

This page is about what to do when the answer is no. For a section-by-section look at the entry rights themselves, see rights of access under the Party Wall etc. Act 1996. For commercial-scale scaffolding and crane agreements, see scaffolding licences, crane oversail agreements and the Party Wall Act.

Route 1: Party Wall Act entry

Section 8 lets the building owner, their builders, agents and surveyors enter the neighbour's land during usual working hours to carry out work "in pursuance of this Act". They can remove furniture or fittings if needed. Appointed surveyors have a matching right to enter to carry out their role (s.8(5)).

The limits matter:

  • It's tied to notified work. The right exists for work the Act covers. If you haven't served a valid notice, section 8 doesn't help you.
  • 14 days' written notice. Serve it at least 14 days before the day of entry. In an emergency, give whatever notice is reasonably practicable.
  • Not a general licence. The GOV.UK booklet says access is only for works under the Act. It doesn't treat scaffolding as an automatic right, and encourages neighbours to allow access voluntarily for things like scaffolding and pointing, because the finish is often better.
  • Damage and inconvenience. You must not cause unnecessary inconvenience (s.7(1)) and must compensate for any loss or damage (s.7(2)).

Whether scaffolding falls within section 8 depends on whether it is genuinely needed to carry out the notified work, rather than being a convenience for the wider build. That's a question for the surveyors and, if it comes to it, a court. Don't assume it.

When the neighbour still refuses

If you have served notice correctly, the Act provides real teeth. An occupier who refuses entry to someone they know is entitled to it commits an offence, as does anyone who obstructs that entry (s.16). Prosecution is in the magistrates' court. If the premises are closed, entry can be forced, but only with a police officer present (s.8(2)). In practice, surveyors try hard to avoid either step. A letter from your surveyor explaining the legal position usually resolves things.

If your neighbour is refusing a surveyor rather than your builders, see what to do if a neighbour refuses access to a party wall surveyor.

Route 2: an access order under the 1992 Act

The Access to Neighbouring Land Act 1992 applies in England and Wales and is aimed at preservation, not development. The court can make an order if the works are reasonably necessary to preserve your land and can't be done, or would be substantially more difficult, without going onto next door's land.

The Act lists "basic preservation works" that automatically count as reasonably necessary (s.1(4)):

  • maintaining, repairing or renewing part of a building or structure;
  • clearing, repairing or renewing drains, sewers, pipes or cables;
  • treating, cutting back or removing a dead, diseased, damaged, dangerous or insecurely rooted tree, hedge or shrub;
  • filling in or clearing a ditch.

Work that incidentally involves alteration, improvement or demolition can still qualify if the court thinks that fair and reasonable (s.1(5)). An extension or loft conversion on its own is unlikely to qualify, because it is development, not preservation.

What the court can attach to an order (s.2):

  • conditions on how and when the work is done, who can enter, and precautions;
  • compensation for loss, damage, injury, or substantial loss of privacy or inconvenience;
  • insurance against specified risks;
  • a record of the condition of your neighbour's land before work.

The court can also order a payment for the right of entry itself, based on the advantage you gain. That payment can't be ordered where the works are to residential land, meaning a dwelling and its garden, yard, garage or outbuildings (s.2(5), s.2(7)).

An agreement that tries to sign away the right to apply for an order is void (s.4(4)). Applications start in the county court. Because there are court fees and the risk of paying the other side's costs, this route is a last resort.

Route 3: a negotiated access licence

For most domestic projects, the realistic answer is a licence: a written agreement giving your builders permission to enter, put up scaffolding or swing a crane over the neighbour's land on agreed terms.

Points to cover:

  • what will go where, with a sketch;
  • start and end dates, and what happens if the job overruns;
  • working hours and who may enter;
  • protection for plants, paving and windows, and how the area is left;
  • a condition record or photographs before scaffolding goes up;
  • insurance (ask your scaffolder for proof of public liability cover);
  • security, such as alarms on scaffold near windows;
  • any fee, and whether it is a lump sum or weekly.

Fees are negotiated, not set by law. No Act sets a scaffolding licence fee. The Party Wall Act gives no right to charge for section 8 entry, and the 1992 Act rules out a payment for the right of entry to residential land. If you're asking for a licence because no statute gives you access, your neighbour can ask for a fee, and you can say no. Our fee research (see the cost guide) found no reliable published figures for domestic scaffold licence fees, so we don't quote one.

If your neighbour says no to a licence, ask your builder or architect about alternatives: a cantilevered or birdcage scaffold kept on your side, building the wall from inside ("overhand" bricklaying), or a facing material that needs no outside finishing.

Example access-request letter outline

Write first, before any formal notice. A clear, specific request is far more likely to get a yes. Build your letter around these points:

  1. Who and where. Your name, your address, and theirs.
  2. What's being done. One or two sentences on the project, and whether a party wall notice or award is already in place.
  3. Exactly what access you need. For example: "a two-lift scaffold along the 6-metre flank wall, standing 1.2 metres into your side passage".
  4. How long. Proposed dates, and the longest it could reasonably take.
  5. How you'll protect their property. Boards over paving, sheeting, a photo record beforehand, and an offer for them or their surveyor to inspect.
  6. Insurance and contacts. The scaffolder's insurer, and a phone number for the site manager.
  7. Making good. A promise to put right any damage, at your cost, promptly.
  8. What you're offering. If you're proposing a fee or other goodwill gesture, say so clearly.
  9. Ask for a reply by a date. Give at least a week or two. Offer to meet on site.

Keep it polite and factual. If the work is under the Party Wall Act, a separate section 8 notice of entry follows, giving at least 14 days.

Frequently asked questions

Can a neighbour refuse scaffolding on their land?

Usually, yes. Unless the scaffold is genuinely needed for notified Party Wall Act work, or the work is a qualifying repair under the 1992 Act and a court grants an order, putting scaffolding on someone else's land without permission is trespass. Ask early, offer protection and insurance, and consider a scaffold design that stays on your side.

Can my neighbour charge for scaffolding access?

For a voluntary licence, they can ask; you can negotiate or refuse. They can't charge for section 8 entry under the Party Wall Act, though you must pay for any damage. A court making a 1992 Act order can't award a fee for entry to residential land.

Does a party wall award deal with scaffolding?

It can deal with access needed for the notified work, including how it's done and how the neighbour's property is protected. Surveyors generally avoid using the award as a back door to scaffolding that isn't needed for the Act work. If scaffolding is mainly for the wider build, expect to agree a separate licence.

Can my neighbour refuse access for repairs to my wall?

If the repair can't reasonably be done from your side, you can apply to the county court for an access order. The court weighs your need against the disruption to your neighbour and can attach conditions and compensation.

Related guides

Last updated: 4 November 2026. This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

Section 8 in detail

Where work is being carried out under the Party Wall Act, section 8 gives the building owner, their workmen and surveyors the right to enter the neighbour's land and premises "at all usual times" to carry out the notified work, and gives appointed surveyors a right of entry to carry out their functions. The building owner must give at least 14 days' notice of intended entry, except in an emergency, when notice must be given as soon as possible. If the premises are closed, the building owner may, if accompanied by a police officer, break open fences or doors to enter (section 8(3)). Obstructing someone exercising these rights is a criminal offence under section 16.

In practice, forced entry is a last resort that almost never happens. The existence of the right usually brings a reasonable conversation.

Access for work outside the Party Wall Act

If your work does not fall within the Act, for example repointing your own flank wall or clearing your own gutters from next door's garden, section 8 does not help. You need your neighbour's permission, usually recorded in a short access licence. If the work is basic preservation work to your property and permission is refused, you can apply to the county court under the Access to Neighbouring Land Act 1992 for an access order.

What a good access licence covers

  • Dates and working hours.
  • Exactly which part of the neighbour's land will be used, with a plan.
  • Scaffolding: design, alarms, security and the removal date.
  • Protection of plants, paving and fences, and a condition record before and after.
  • Insurance and responsibility for damage.
  • A fee for the use of the land, if agreed (common for long scaffold periods).

If you are the neighbour being asked for access

  • Ask whether the work is under the Party Wall Act. If it is, your surveyor (or the agreed surveyor) can include access terms in the award.
  • Ask for a written licence for anything else, and for a record of the condition of your garden or property first.
  • Ask for proof of the contractor's insurance.

Scaffold and crane oversail

Scaffolding that projects over your neighbour's land, or a crane jib that swings over it, is a trespass into their airspace without permission. Developers usually agree oversail licences. See our guide to scaffold licences and oversailing.

Download the Party Wall etc. Act 1996 free

Get the full, up-to-date text of the Act as a PDF from the official legislation.gov.uk record, with our plain-English guide to every section, sent straight to your inbox.