What happens after party wall works finish

When the building work ends, the party wall process is not quite over. The surveyors usually inspect the finished work against the schedule of condition, any damage is made good (or paid for), the surveyors' fees are settled, and everyone files the papers. The Act has no formal "closing" form, so how this goes depends on what your award says and on how your surveyors work. The steps below are the usual sequence.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

What the Act does and does not say

The Act sets up the notices, the award and the surveyors' powers. It says very little about the end of the job. The relevant points are:

  • The award can deal with the right to do the work, the time and manner of doing it, and incidental matters including costs (section 10(12)).
  • The reasonable costs of making the award and of reasonable inspections of the work are paid by whoever the surveyors decide (section 10(13)).
  • Where the building owner is required to make good damage, the adjoining owner can ask for money instead (section 11(8)).
  • Surveyors appointed under the Act can enter the premises at usual working hours on proper notice to do their job (section 8).

There is no statutory certificate of completion and no registry filing. So the "close" of a party wall award is mostly a matter of practice: confirm the work is done, confirm the damage is dealt with, settle the money, and keep the paper.

Step 1: Tell your surveyor the work is finished

If you are the building owner, tell your surveyor (or the agreed surveyor) when the work in the award is complete. Do not wait for them to notice. If the award says the surveyors must be told at particular stages, such as after foundations are in, make sure those were met; a missed stage is easier to sort out now than in a year.

Neighbours can ask too. If you are the adjoining owner and you have a surveyor, ask them to arrange the final visit. If you do not, your own inspection of your property is what matters.

Step 2: Final inspection against the schedule of condition

The schedule of condition is a written, usually photographed record of the neighbour's side before work began. The explanatory booklet describes it as the way to tell later whether the works caused a problem, and it advises one for that reason. The final inspection puts the "before" and "after" together.

A sensible final inspection goes room by room, wall by wall, in the same order as the schedule:

  1. Walls and ceilings adjoining the works: hairline cracks, new cracks, plaster that has lifted.
  2. Joints and corners: gaps between walls and ceilings, around door frames and window reveals.
  3. Chimney stacks, flues and roof junctions where the works met your roof.
  4. Garden walls, paths and outbuildings if they were recorded.
  5. Anything the award required, such as flashings, weathering, parapets or reinstated finishes.

Cracks already in the schedule are not new damage. An unrecorded fine crack may be seasonal movement or the works, which is a judgement for the surveyors.

If a new defect shows up, photograph it with a ruler for scale, mark the date, and tell the surveyors in writing. Our guide on what evidence is needed to prove damage lists what helps.

Step 3: Making good

Where the Act requires the building owner to make good damage to the adjoining property, they are responsible for repairing it, including damage to internal decorations and furnishings in many cases (see section 2). The choices usually are:

Option What happens When it suits
Building owner's builder repairs Their contractor returns and makes good to an agreed standard Small, clear damage and good relations
Payment instead (section 11(8)) You receive a sum equal to the cost, set by agreement or by the surveyors under section 10 You want your own contractor, or do not want site workers back in your home
Staged: monitor, then repair Wait a season, then re-inspect Fine cracks that may still be moving

Agree a standard of finish (filler and paint, re-skim, or redecorating the room) and have the surveyors record it. Our page on who pays for damage during building covers the money, and the claiming compensation guide covers disputes.

Step 4: Check the work against the award

The award is a set of instructions, so the final check also asks whether the building owner did what it said. Look at:

  • Position and depth of foundations or beams against the agreed drawings.
  • Protection and weathering: has the roof junction been flashed properly, and is the party wall weathered?
  • Chimney and flue arrangements, which the Act expects to be carried up to an agreed height where affected.
  • Access and hours: were the working hours kept? Complaints go in writing to the surveyors, not on the doorstep.
  • Any special conditions: monitoring readings, vibration limits or temporary works.

If the work departs from the award, the Act (section 7(5)) says deviations must be agreed or determined by the surveyors. Raise it immediately; it is far harder to fix after the scaffolding is gone.

Step 5: The final account and the fees

Each surveyor sends an invoice. The award normally says who pays, and under section 10(13) the surveyors decide who bears the reasonable costs. Commonly the building owner pays the reasonable fees of both surveyors where the work is for their benefit, though it is not automatic and the award can say otherwise. Fees and extras, such as additional visits or a post-works inspection, may be charged separately. One commercial guide (BookaBuilderUK, June 2026) puts extra inspections at roughly £100 to £300 a visit; treat that as indicative only, since firms and regions differ. Our surveyor cost guide has the wider picture.

Before paying:

  1. Check the invoice matches what the award said about who pays.
  2. Check extra charges against what was agreed at the start.
  3. If something looks wrong, ask the surveyor for a breakdown. The reasonable costs test applies. See how to dispute a surveyor's fees.

If you are an adjoining owner and your surveyor sends you an invoice, check the award first. It normally says the building owner pays reasonable fees, so ask before you pay.

Step 6: Closing the award

Because nothing in the Act closes an award, ask your surveyor to confirm in writing that:

  • the works are complete;
  • the final inspection has taken place and its outcome;
  • any damage has been made good, or paid for;
  • no further claims are known; and
  • fees have been settled.

Some surveyors issue a completion letter or note as a matter of course, others do not unless asked. It costs little and gives you a clean end-point. It also helps if a buyer's solicitor later asks.

If security for expenses was held, which the Act allows under section 12, ask for it to be released once everything is done. Our guide on security for expenses explains it.

Step 7: Keep the papers

Keep these together, on paper or in a labelled digital folder, and tell your family where they are:

  • the notices and any consents or acknowledgements;
  • the award and the plans attached to it;
  • the schedule of condition and photographs;
  • the final inspection notes and completion letter;
  • the surveyors' final invoices and proof of payment;
  • insurance certificates for the work.

The explanatory booklet suggests keeping the award with the property deeds. After completion, the neighbour may also ask for plans and sections of the finished work.

How long? The Act sets no retention period. A practical rule is to keep the papers for as long as you own the property, then hand them on. The reason is the time limits on claims. For property damage in negligence, the Limitation Act 1980 as amended by the Latent Damage Act 1986 allows the later of six years from the damage or three years from when you could reasonably have known about it, with a longstop of 15 years from the negligent act. A crack that shows up years later may still be in time, and your records are how you prove what was there before.

Selling or buying afterwards

When you sell, the buyer's solicitor may ask about building work and paperwork. Having the notice, award, completion letter and any building regulation certificate to hand avoids delay. Buying? Ask for the papers before exchange; see buying a house with an outstanding dispute. Where no award exists, never backdate or invent paperwork.

Frequently asked questions

Is there a formal end to a party wall award?

No. The Act has no completion form. The practical end is when the work is complete, the final inspection is done, damage is dealt with and fees are paid. Ask for written confirmation.

Do I have to have a final inspection?

The Act does not require one, but the surveyors can carry out reasonable inspections and their costs can be allocated under section 10(13). A final inspection is good practice, especially where a schedule of condition exists.

What if I notice damage months after the work?

Tell the building owner and your surveyor in writing at once, compare with the schedule, and photograph it. The award may no longer be live, so you may need a fresh claim. Time limits apply, so take advice early.

Can I get the neighbour to pay for redecorating?

Where the Act requires them to make good damage, that can include internal decorations. Agree the standard early. If you cannot agree, section 10 gives you the surveyors' route.

How long should I keep the party wall papers?

For as long as you own the property, and pass them on when you sell. The Act sets no minimum. Claims for hidden damage can arise years later.

Last updated: 4 November 2026. This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

Download the Party Wall etc. Act 1996 free

Get the full, up-to-date text of the Act as a PDF from the official legislation.gov.uk record, with our plain-English guide to every section, sent straight to your inbox.

We use your email to send the Act. See our privacy notice.

Contact us

Send us a message and we'll reply by email.

We only use your details to reply to you. A quick human check runs when you send.