PartyWallAgreement.org.uk

Party wall notice periods: how much notice you must give

You must give at least one month's notice for a new wall on the boundary (Section 1) or for excavation near a neighbour's building (Section 6), and at least two months' notice for work to an existing party wall or party structure (Section 3). Your neighbour then has 14 days to reply. Work to a party wall can start sooner only if the neighbour agrees in writing.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

The notice periods at a glance

Type of workNoticeMinimum periodSectionLapses if not started
New party wall or party fence wall astride the boundaryLine of junction notice1 month1(2)No lapse rule in s.1
New wall wholly on your own land, up to the boundaryLine of junction notice1 month1(5)No lapse rule in s.1
Work to an existing party wall or structure (beams, cutting in, raising, underpinning, chimney breasts)Party structure notice2 months3(2)(a)12 months, s.3(2)(b)
Excavating within 3 m or 6 m of a neighbour's building, to the depths in s.6Notice of adjacent excavation1 month6(5)12 months, s.6(8)

These are minimums. The notice must give a proposed start date that is no earlier than the end of the period. The periods come from the Act itself, which you can read on legislation.gov.uk.

How the periods are counted

The clock starts on the day the notice is served, not the day you wrote it. Service depends on the method: handing it over, posting it to the owner's usual or last known address, or email where the owner has agreed to receive notices by email. If you post a notice, allow for delivery before you count. A month means a calendar month, so a notice served on 10 March gives a one-month earliest start of 10 April and a two-month earliest start of 10 May.

Many building owners give a margin of a week or so beyond the minimum. If the start date in your notice turns out to be too early because service was late, the safest fix is to serve a fresh notice rather than argue about it later.

The 14-day reply window

Separately from the notice period, the neighbour has 14 days from service to consent in writing:

  • Section 3 and Section 6 notices: no written consent within 14 days means the neighbour is treated as dissenting, and a dispute is deemed to have arisen (sections 5 and 6(7)). Surveyors are then appointed.
  • Section 1 notice for a wall astride the boundary: no consent within 14 days means you can only build the wall wholly on your own land, at your own expense (section 1(4)). It does not by itself create a surveyor dispute.

So the 14 days and the one or two months run at the same time. The surveyor process, if needed, also happens inside the notice period where possible. If it is not finished, you should not start work that is in dispute until an award is made.

Worked example: loft conversion with an excavation as well

Sam plans a loft conversion with steel beams into the party wall, and a small rear extension whose foundations go deeper than the neighbour's, 2 metres away.

  1. 1 March: Sam hands the neighbour a party structure notice (2 months) and a notice of adjacent excavation (1 month). Both are served that day.
  2. 15 March: The 14 days end. The neighbour has not replied, so both notices are in dispute.
  3. 15 March: Sam serves a 10-day request asking the neighbour to appoint a surveyor.
  4. 25 March onwards: No reply, so Sam can appoint a surveyor for the neighbour under section 10(4). The surveyors prepare a schedule of condition and award.
  5. 1 April: The earliest date for the excavation, if the award is in place.
  6. 1 May: The earliest date for the beams, unless the neighbour agrees in writing to an earlier start.

Sam's builder cannot start the loft steels in April just because the extension has started. Each notice has its own period. Our party wall timeline flowchart shows the same sequence visually.

Can work start before the notice period ends?

For party structure work, yes, with written consent. Section 3(3)(a) says nothing in section 3 prevents a building owner exercising the section 2 rights with the written consent of the adjoining owners and occupiers. The GOV.UK booklet adds that the neighbour may agree to an earlier start but does not have to.

The Act has no equivalent wording in Sections 1 or 6. In practice, where the neighbour consents and an earlier start is agreed in writing, or an award settles the timing, surveyors deal with it. Section 10(12) also says that, unless the owners agree otherwise, a period set in an award for doing work does not start until the statutory notice period has expired. If you want to start early, get it in writing and keep it with your notice.

When to serve: a practical guide

  • Not too early. Section 3 and Section 6 notices lapse if work has not started within 12 months and is not being carried on with due diligence. See how long a party wall notice lasts.
  • Not too late. Serve as soon as your design is fixed enough to describe the work and, for Section 6, produce plans and sections. Two months for a loft is the bare minimum, and a two-surveyor award can take longer.
  • After planning, ideally. If the design may change at planning, waiting saves serving twice. Planning permission and the Act are separate, though; see Party Wall Act vs planning vs building regulations.
  • Know which notices apply. Our free party wall notice checker helps you work out which sections your project triggers.

Other time limits you may meet

StepTime limitSection
Counter notice by the neighbourWithin 1 month of the party structure notice4(2)(b)
Request to appoint a surveyor10 days to respond10(4)
Notice of entry to a neighbour's landAt least 14 days, except in an emergency8(4)
Appeal against an awardWithin 14 days of service of the award10(17)
Security for expenses requirementLapses if not met within 1 month12(3)

Frequently asked questions

Is the party wall notice period for a loft conversion one or two months?

Usually two months, because steel beams or other work into the party wall is Section 2 work needing a party structure notice under Section 3. If the loft also involves excavation, that part needs its own one-month Section 6 notice.

Does the 14-day reply period come out of the notice period?

Yes, it runs at the same time. The notice period is the minimum gap before work starts; the 14 days is how long the neighbour has to consent.

Can my neighbour make me wait longer than the notice period?

Not just by asking. But if they dissent, you should not start disputed work until the surveyors have made an award, and that can take longer than the minimum period.

Do weekends and bank holidays count?

The Act counts in months and days without excluding weekends. Calendar dates are what matter. If a deadline matters to you, count conservatively and add a margin.

What if I already started before the period ended?

Stop the notifiable work and take advice. Starting early without written consent exposes you to an injunction and a damages claim. See what happens when work starts without an agreement.

This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

Download the Party Wall etc. Act 1996 free

Get the full, up-to-date text of the Act as a PDF from the official legislation.gov.uk record, with our plain-English guide to every section, sent straight to your inbox.

We use your email to send the Act. See our privacy notice.

Contact us

Send us a message and we'll reply by email.

We only use your details to reply to you. A quick human check runs when you send.