Most extensions, loft conversions and basements next to a neighbour need at least one party wall notice, but plenty of building work doesn't. Use the checker below to see which notices your plans need, how far ahead to serve them and what happens if your neighbour doesn't reply.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

Do I need a party wall notice?

Answer a few questions to see which notices your project needs, how much notice to give and how long your neighbour has to reply. Works for England and Wales.

1. Where is the property?
2. What does your project involve? Tick all that apply.
3. Where will the new wall stand?
4. About the excavation

Measure the distance horizontally from the outside face of their wall to the nearest edge of your excavation. Depths are from the same ground level.

General guidance on the Party Wall etc. Act 1996, not legal advice. A party wall surveyor can confirm what your plans need.

The three notices, in short

Notice When you need it Minimum notice If your neighbour doesn't reply in 14 days
Line of junction (section 1) Building a new wall on or up to the boundary where there's no wall now 1 month A wall astride the boundary must be built wholly on your land instead
Party structure (section 3) Work to an existing shared wall: beams, chimney breast removal, raising, underpinning, cutting in 2 months A dispute is treated as having arisen and surveyors are appointed
Adjacent excavation (section 6) Digging within 3 m of a neighbour's building below their foundations, or within 6 m and below a 45° line from them 1 month A dispute is treated as having arisen and surveyors are appointed

One letter can cover more than one type of work, but each notice must meet its own rules. A section 3 or section 6 notice stops having effect if the work hasn't started within 12 months.

How the excavation test works

The 3 metre rule catches digging close to your neighbour's house, garage or other structure that goes deeper than the bottom of their foundations. The 6 metre rule reaches further out but only catches deeper digs: picture a line running down at 45° from the bottom of their foundations towards your site. If any part of your excavation within 6 metres goes below that line, you need notice.

As a quick check, at any point within 6 metres, the line sits at their foundation depth plus your horizontal distance from their wall. If your neighbour's foundations are 0.8 m deep and you dig 4 m away, the line is 4.8 m down there, so an ordinary 1.2 m strip footing wouldn't trigger the 6 metre rule, though deep piles might.

When you don't need a notice

Fixing shelves or kitchen units, adding sockets, rewiring and replastering a shared wall usually fall outside the Act. So does building wholly on your own land away from the boundary when you aren't digging near a neighbour's foundations. The Act covers England and Wales only.

Next steps

If the checker says you need notice, you can create a notice with our free generator, read what to do once notice is served, or find a party wall surveyor near you. If you're on the receiving end, see I have received a party wall notice.

Last updated: 4 November 2026. This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.