Section 6 party wall notice: excavating within 3 or 6 metres of a neighbour

A Section 6 party wall notice, also called a notice of adjacent excavation, is needed when you dig, or dig and build, within 3 metres of a neighbour's building and go deeper than the bottom of its foundations, or within 6 metres where your dig would cut a line drawn down at 45 degrees from the bottom of those foundations. You must serve it at least one month before you start, with plans and sections showing where and how deep you will dig. If your neighbour doesn't consent in writing within 14 days, a dispute arises and surveyors decide how the work proceeds.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

Do I need a party wall notice?

Answer a few questions to see which notices your project needs, how much notice to give and how long your neighbour has to reply. Works for England and Wales.

1. Where is the property?
2. What does your project involve? Tick all that apply.
3. Where will the new wall stand?
4. About the excavation

Measure the distance horizontally from the outside face of their wall to the nearest edge of your excavation. Depths are from the same ground level.

General guidance on the Party Wall etc. Act 1996, not legal advice. A party wall surveyor can confirm what your plans need.

Why Section 6 exists

When you dig near a building, the soil supporting its foundations can move. A trench for a rear extension, a basement, a lift pit, a soakaway or a row of piles can all undermine next door if done carelessly. Section 6 of the Party Wall etc. Act 1996 doesn't stop the work. It makes you warn your neighbour, explain the plan, and protect their foundations where needed.

Unlike Sections 1 to 3, Section 6 doesn't need a shared wall at all. Detached houses are caught if they are close enough. A garage, outbuilding or garden wall can count too, because the Act refers to the neighbour's "building or structure".

The 3 metre rule (s.6(1))

Section 6 applies where you plan to excavate, or excavate and build, within 3 metres measured horizontally from any part of your neighbour's building or structure, and any part of the work within that 3 metres will go lower than the bottom of their foundations.

Two tests, both must be met:

  1. Distance. Is any part of your excavation within 3 m, measured horizontally, of any part of their building or structure?
  2. Depth. Within that 3 m, does any part go below the level of the bottom of their foundations?

The comparison is between levels, not between depths from your own ground. If your garden sits 500 mm lower than next door's, a trench that looks shallow on your side may still reach below their footing.

The 6 metre rule and the 45 degree line (s.6(2))

Section 6 also applies where your work is within 6 metres measured horizontally of the neighbour's building or structure, and any part of it within that 6 m will meet a plane drawn downwards at 45 degrees to the horizontal. The plane starts from the line where the level of the bottom of their foundations meets the outside face of their external wall.

Picture it from the side. Start at the bottom of their footing, at the face of their wall. Draw a line sloping down and away from their house at 45 degrees. Because it's 45 degrees, for every metre you move away horizontally, the line drops one metre. Anything you dig that crosses below that line, within 6 m, is caught.

A quick way to check: the 45° line's depth at any point = the depth of their foundation + your horizontal distance from their wall. Dig deeper than that number, within 6 m, and you need a notice.

How the two rules fit together

Your distance from their building Notice needed if your dig goes deeper than… Rule
0–3 m the bottom of their foundation s.6(1)
0–6 m the 45° line (their foundation depth + your distance) s.6(2)
More than 6 m No Section 6 notice —

Within 3 m the first rule bites first, because their foundation level is always shallower than the 45° line. Between 3 and 6 m only the 45° rule applies, which in practice catches deep work: basements, piling, deep drainage and lift pits.

Worked examples with numbers

All examples assume the neighbour's footing bottoms out 1.0 m below ground, and both gardens are level.

Example A: rear extension trench at 2 m. You dig a 1.2 m deep strip foundation 2 m from next door's back wall. It is within 3 m, and 1.2 m is lower than their 1.0 m footing. Notice needed under the 3 m rule.

Example B: shallow trench at 2 m. Same position, but your engineer specifies a 0.9 m deep foundation. It's within 3 m but not lower than their footing. No Section 6 notice under the 3 m rule, and the 45° line at 2 m is 3.0 m deep, so the 6 m rule doesn't catch it either.

Example C: trench at 4.5 m. A 1.5 m deep trench 4.5 m from their house. Beyond 3 m, so only the 6 m rule can apply. The 45° line here is 1.0 + 4.5 = 5.5 m deep. Your 1.5 m trench is well above it. No notice.

Example D: piles at 5 m. Your extension sits on piles 12 m deep, 5 m from next door. The 45° line is 1.0 + 5.0 = 6.0 m deep. Your piles go to 12 m. Notice needed under the 6 m rule. See piled foundations near a neighbour.

Example E: basement at 1 m. A 3.5 m deep basement 1 m from the party wall line of a terrace. Clearly caught by the 3 m rule. Basements usually also involve underpinning the party wall itself, which is a Section 2 right needing a Section 3 party structure notice with two months' notice.

Example F: you don't know their foundation depth. This is common with older houses. Surveyors often dig a trial pit or assume a shallow Victorian footing. If in doubt, serve the notice. The cost of a notice is small next to the cost of an injunction or a damage claim.

What the notice must include

Contents (s.6(5))

Serve the notice at least one month before you start. It must set out your proposals and state whether you propose to underpin, strengthen or otherwise safeguard your neighbour's foundations. As with other notices, give your name and address, the address of the work, the date you plan to start, and a statement that it is served under the Act.

Plans and sections (s.6(6))

The notice must come with plans and sections showing:

  • (a) the site and depth of any excavation, and
  • (b) where you are putting up a building or structure, its site.

A plan is the view from above, so it shows where the dig is in relation to the neighbour's house. A section is a vertical slice, showing how deep you go relative to their foundations. Your architect's or engineer's drawings usually do the job, provided the neighbour's building and the dig depths are shown clearly. A notice served without them risks being invalid.

Who to serve

Every owner whose building or structure is within the 3 m or 6 m zone counts as an adjoining owner for Section 6, even if their land doesn't touch yours (s.6(4)). The GOV.UK booklet points out that this can include owners with other land in between. On a terrace, a deep basement can mean notices to several houses.

Underpinning and safeguarding (s.6(3))

Section 6(3) gives you the right to underpin, strengthen or otherwise safeguard your neighbour's foundations, at your own expense, as far as necessary. If your neighbour requires it, you must do so, again at your expense.

In practice, "safeguarding" can range from underpinning their footing to temporary propping, sheet piling, or digging in short sections ("hit and miss") so the soil never stands open for long. The surveyors' award usually sets out the method, with the engineer's details attached.

Section 6 adds three more protections for your neighbour:

  • Particulars after completion (s.6(9)). When the work is finished, your neighbour can ask for details of what was done, including plans and sections.
  • No escape from liability (s.6(10)). Serving a notice doesn't relieve you of liability for any injury to your neighbour caused by the work.
  • General duties (s.7). You must not cause unnecessary inconvenience, you must compensate for loss or damage, and you must provide shoring or temporary works where needed. See temporary works and shoring.

Response, dispute and timing

Your neighbour has 14 days, starting on the day of service, to serve written consent. If they don't, they are deemed to have dissented and a dispute arises (s.6(7)). From there it's the section 10 route: one agreed surveyor, or one each plus a selected third surveyor. If your neighbour won't appoint anyone within 10 days of a written request, you can appoint a surveyor for them (s.10(4)).

The notice lapses if work hasn't begun within 12 months of service and isn't being pursued with due diligence (s.6(8)).

A realistic sequence for a rear extension:

  1. Week 0: engineer confirms foundation depth; you check distances against the 3 m and 6 m rules.
  2. Week 1: serve the Section 6 notice with plans and sections (and any Section 1 or 3 notices in the same letter).
  3. Week 3: 14 days pass. Consent received, or a dispute arises and surveyors are appointed.
  4. Weeks 3–8: schedule of condition of next door, award agreed and served.
  5. Week 5 onwards: earliest start under Section 6 (one month), once any award is in place. If a Section 3 notice is also involved, the two-month period governs.
  6. Award plus 14 days: the appeal window closes (s.10(17)).

Mistakes to avoid

  • Measuring from the boundary instead of their building. The 3 m and 6 m distances run from any part of the neighbour's building or structure, not from the fence.
  • Forgetting outbuildings. A neighbour's garage or garden wall can be a "structure". See shallow foundations and digging deeper.
  • Leaving out the drawings. Section 6(6) makes plans and sections mandatory.
  • Assuming silence is consent. It's deemed dissent.
  • Thinking detached houses are exempt. Distance and depth decide, not whether you share a wall.

Typical costs

For a rear or side extension with excavation within 3 m, BookaBuilderUK (June 2026) gives about £1,000–£2,500 with an agreed surveyor, possibly over £3,000 for a mid-terrace. Where each side has its own surveyor, published ranges run to roughly £2,400–£3,500 or more (HomeOwners Alliance; BestBuilders). Basements start around £1,800–£2,700 agreed and can exceed £5,000 for complex London schemes. These are indicative figures; see the party wall surveyor cost guide and our budget calculator.

Frequently asked questions

Does the 3 metre rule apply to a detached house?

Yes. Section 6 is about distance and depth, not shared walls. If your trench is within 3 m of your neighbour's detached house, garage or other structure and goes below their foundations, you need a notice, even with a driveway and fence between you.

How do I find out how deep my neighbour's foundations are?

Ask; they may have drawings. Otherwise an engineer can estimate from the age and type of building, and a trial pit on your side can confirm it. Many surveyors take a cautious view: if your dig might go below their footing, they serve the notice.

Do I need a Section 6 notice for a garden room on ground screws?

It depends on depth and distance. Ground screws can go a metre or more into the ground. If any are within 3 m of next door's building and deeper than its footing, or within 6 m and below the 45° line, the rule applies. Check the manufacturer's depth and measure.

Can my neighbour stop me digging?

No. Section 6 lets you proceed once notice and any award are in place. Your neighbour can require you to underpin or safeguard their foundations at your expense, and surveyors can control the method and timing. Planning and building regulations are separate. See dealing with an unreasonable adjoining owner.

Is the notice period one month or two?

One month for Section 6 (s.6(5)). If the same project also cuts into or underpins a party wall, the Section 3 notice needs two months, so plan around the longer period.

Can one notice cover excavation and a new wall?

You can send them in one letter. The GOV.UK booklet says the example letters may be combined. But each part must meet its own section's rules: Section 6 needs plans and sections and a statement on safeguarding; Section 1 needs a description of the wall.

What if my builder has already started digging without a notice?

Stop and serve a notice now. The Act still applies to work that has begun. Your neighbour could seek an injunction or claim damages. Read what to do if a neighbour starts work without telling you and the retrospective procedure.

Related guides

Last updated: 4 November 2026. This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

Download the Party Wall etc. Act 1996 free

Get the full, up-to-date text of the Act as a PDF from the official legislation.gov.uk record, with our plain-English guide to every section, sent straight to your inbox.