Section 1 party wall notice: building a new wall on the line of junction
A Section 1 party wall notice is the notice you must give your neighbour at least one month before you build a new wall on, or right up to, the boundary between your land and theirs, where no wall of a building stands there yet. If you want the wall to straddle the boundary, your neighbour must agree in writing within 14 days; if they don't, you can still build, but only wholly on your own land and at your own cost. The rules are in section 1 of the Party Wall etc. Act 1996, which applies in England and Wales.
When Section 1 applies (and when it doesn't)
Section 1 covers fresh building at the "line of junction", which is the Act's phrase for the boundary between two properties in different ownership. It applies only where, at that line, the land is either:
- not built on at all (for example, an open side garden, a gap between two detached houses, or a vacant plot), or
- built on only with a boundary wall that is not a party fence wall and not the outside wall of a building. In practice that means a wall that stands wholly on one owner's side (s.1(1)).
If there is already a party wall or a party fence wall at the boundary and you want to raise, thicken or rebuild it, you are in Section 2 territory, not Section 1. See our guide to Section 2 rights over existing party walls.
Typical projects that trigger a Section 1 notice:
- a single-storey side extension whose new flank wall sits on the boundary
- a detached garage or garden room with a masonry wall built up to the boundary
- a new brick garden wall built along the boundary line
- a new house on an infill plot where the side wall lands on the line
What it does not cover: timber fences, hedges and other non-masonry boundary treatments. The GOV.UK booklet says plainly that wooden fences are not party fence walls. For more on garden boundaries, see when the Act applies to garden walls and fences.
Two choices: astride the boundary or wholly on your land
The single most important decision in a Section 1 project is where the wall will sit. The Act treats the two positions very differently.
| Wall astride the boundary (a party wall or party fence wall) | Wall wholly on your own land, up to the boundary | |
|---|---|---|
| Section | s.1(2)–(4) | s.1(5)–(7) |
| Notice | At least 1 month, describing the wall | At least 1 month, describing the wall |
| Neighbour's consent needed? | Yes, written consent | No |
| If neighbour stays silent for 14 days | You lose the right to build astride; you may build only on your own land | Nothing changes; you may start after 1 month |
| Who pays | Shared in proportion to each owner's use (s.1(3)) | You pay everything (s.1(7)) |
| Footings under neighbour's land | Part of the agreed design | Projecting footings allowed only where necessary, in a set window (s.1(6)) |
| Compensation | Usually dealt with in the agreement | You must compensate for damage caused (s.1(7)) |
Option A: building astride the boundary
You serve a notice under s.1(2) at least one month before work starts, describing the wall you intend to build. If your neighbour serves a notice of consent, the wall is built half on each side of the line, or in whatever other position you both agree (s.1(3)(a)).
The cost is then split between you. The Act does not say 50:50. It says the cost is shared in proportions that reflect the use each of you makes (or will make) of the wall, using labour and material prices current at the time that use happens (s.1(3)(b)). So if you build a two-storey wall and your neighbour only uses the bottom metre as a garden wall, they should not be paying half.
If your neighbour does not consent in writing within 14 days of being served, you can only build the wall at your own expense, as an external wall or fence wall placed wholly on your own land (s.1(4)). Note the key difference from Section 3 and Section 6 notices: silence here does not create a dispute. It simply takes the astride option off the table.
Option B: building wholly on your own land
If you want to build up to the boundary but entirely on your own side, you serve a notice under s.1(5), again at least one month before you start, describing the wall. Your neighbour's consent is not needed for the wall itself. Once the month has passed you can begin.
Your neighbour may still have concerns, about footings, damage or how the work is done. Any dispute arising under Section 1 goes through the surveyor procedure in section 10 (s.1(8)).
Foundations under your neighbour's land (s.1(6))
A wall built tight to the boundary often needs a footing that is wider than the wall. With a wall wholly on your land, the wall face sits on the line, so the footing may have to project under next door's ground.
Section 1(6) gives you the right to place projecting footings and foundations below your neighbour's land, but only:
- where they are necessary for the wall, and
- during a window that starts one month after the notice was served and ends 12 months after the day of service.
Two limits trip people up:
- Special foundations need written consent. The Act defines special foundations as ones that use an assemblage of beams or rods to spread a load, which in plain terms usually means reinforced concrete with steel bars or mesh. Section 7(4) says nothing in the Act lets you put special foundations on your neighbour's land without their prior written consent. If your engineer has designed a reinforced strip or raft that crosses the line, you need that consent.
- The window closes. Projecting footings placed after the 12-month period are not covered by s.1(6). If your project stalls, take advice before restarting.
Compensation (s.1(7)) and who pays
Where you build under option B (or under option A after consent was refused), s.1(7) says you must:
- pay for the wall yourself, and
- compensate your neighbour, and anyone occupying their property, for any damage to their property caused by building the wall or placing the footings and foundations.
If your neighbour later builds against your wall and uses it, section 11(11) lets you claim a fair share of the cost, valued at the time they start using it. For more on cost sharing, read can my neighbour make me pay half of a new boundary wall.
Timeline of a Section 1 project
- Design. Fix the wall's position and get the footing design. Check whether it uses reinforcement.
- Day 0: serve the notice. Give your name and address, the property address, and a description and position of the wall. Plans help. The booklet allows service by hand, post, or email if the recipient has agreed.
- Day 14. For an astride wall, the deadline for written consent.
- One month. Work may start and the footing window opens. Earlier only with written agreement.
- If a dispute arises. One agreed surveyor, or one each plus a third (s.10(1)), settle it by award.
- During the work. Section 8 gives a right of entry on 14 days' notice where necessary. See rights of access under the Act.
- Twelve months. The s.1(6) footing window closes.
Worked example: a side extension on the boundary
Priya owns a semi-detached house. She plans a single-storey side extension. The new flank wall will run 6 metres along the boundary with her neighbour Tom's driveway. Nothing is built on the line at present.
Step 1: choose the position. Priya does not want to share a wall with Tom, and Tom has no plans to build. She opts to build wholly on her land, with the outer face of the brickwork on the line.
Step 2: check the footing. Her engineer designs a 600 mm wide concrete strip footing under a 300 mm cavity wall. With the wall face on the line, about 300 mm of footing would sit under Tom's driveway. The footing is unreinforced mass concrete, so it is not a special foundation.
Step 3: serve notices. She serves a Section 1(5) notice on 1 March describing the wall and its position, with a drawing showing the projecting footing. Her extension also involves a trench about 1 metre deep within 3 metres of Tom's garage, deeper than its footings, so she serves a Section 6 notice at the same time. See Section 6 excavation notices.
Step 4: response. Tom needn't consent to the wall. He doesn't reply to the Section 6 notice within 14 days, so a dispute arises on that notice and surveyors are appointed.
Step 5: start. From 1 April Priya may build the wall and place the projecting footing. If the job slipped past the following March, she would lose that s.1(6) right.
If Priya's engineer had specified a reinforced footing instead, she would have needed Tom's written consent to place it under his driveway, or she would have had to redesign it. One common fix is an eccentric (offset) footing kept wholly on her own land.
Mistakes to avoid
- Assuming silence means yes. For an astride wall, it means no.
- Using Section 1 for an existing wall. Raising or rebuilding an existing party fence wall needs a Section 3 party structure notice and two months' notice.
- Treating the notice as a boundary decision. Surveyors cannot decide where the boundary is. Settle that first; see a boundary running down the middle of a garden wall.
What a Section 1 job might cost
Many Section 1 walls proceed without surveyors because the neighbour has nothing to dispute. Where an award is needed, there is little published fee data specific to Section 1. The closest figures are Checkatrade's "new build" range, republished by the HomeOwners Alliance (modified March 2026): about £1,500–£1,800 for an agreed surveyor and £3,000–£3,600 where each side has its own. Treat these as indicative only, and see our party wall surveyor cost guide. You can draft the notice yourself with our free party wall notice templates.
Frequently asked questions
Is there an official Section 1 notice form?
No. The Act does not prescribe a form. The GOV.UK booklet includes example letters for line of junction notices you can adapt. What matters is that the notice says it is served under the Act, gives your name and address, the property address, a clear description of the wall and its position, and the date you plan to start. Our notice generator builds one for you.
Can my neighbour stop me building on my own side of the boundary?
Not under the Party Wall Act. A wall wholly on your land does not need their consent, only one month's notice. They can raise a dispute about matters such as projecting footings, damage or working methods, which surveyors then settle. Planning permission and building regulations are separate, and you still need those where they apply.
Do I need a Section 1 notice for a timber fence?
No. Timber fences, hedges and similar boundary treatments are outside the Act. Section 1 is about walls. A brick or block garden wall built on or up to the boundary is covered, though, so check before swapping a fence for masonry.
What happens if I build without serving a Section 1 notice?
It is not a criminal offence, and councils do not police the Act. But you lose its protection, including the right to place projecting footings under next door's land, and your neighbour could seek an injunction or damages.
How long does a Section 1 notice last?
The Act doesn't put an end date on a Section 1 notice the way Sections 3 and 6 do. But the right to place projecting footings under your neighbour's land exists only from one month to 12 months after service. If the job is delayed beyond that, take advice and consider serving a fresh notice.
Who owns a wall built astride the boundary?
It becomes a party wall (or party fence wall), standing on both properties. Each of you owns the part on your own land, and the Act's Section 2 rights then apply to it. That is why the booklet recommends writing down the agreed position and cost split at the time.
Related guides
- Party Wall etc. Act 1996 summary
- Section 2 rights over existing party walls
- Section 3 party structure notice
- Section 6 excavation within 3 or 6 metres
- Party wall rules for home extensions
Last updated: 4 November 2026. This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.