Free Party Wall Notice Templates & Downloadable Forms

Download a blank notice as a PDF, or use the generator to fill one in on screen. Pick the notice that matches your work, add drawings and serve it properly.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.
Section 1 notice: new wall on the line of junctionAt least 1 month before work. Fillable-by-hand PDF.
Download PDF
Section 3 notice: work to an existing party wallAt least 2 months before work. Covers cutting in, raising, underpinning, inserting beams.
Download PDF
Section 6 notice: excavation near a neighbourAt least 1 month before work. Attach plans and sections.
Download PDF

Use the auto-fill notice generator Cover letter template

How to use a template

  1. Choose the notice that matches your work.
  2. Fill in names, addresses, a description of the work and the start date.
  3. Attach drawings (plans and sections for excavation).
  4. Serve it by hand or by post and keep proof.
  5. Wait 14 days for your neighbour to reply.

Frequently asked questions

Which party wall notice do I need?

It depends on the work. A new wall on the boundary needs a Section 1 notice, work to an existing party wall needs a notice under Section 3 (covering the Section 2 rights), and digging near a neighbour needs a Section 6 notice.

Can I use a template instead of a surveyor?

You can serve a notice yourself. A notice is not the same as an award: if your neighbour dissents or does not reply, surveyors must be appointed.

Is a notice by text or email valid?

Notices should be in writing and served in one of the ways the Act allows, so a signed paper notice by hand or post is the safest route. Check with a surveyor if you plan to serve electronically.

This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

Section 3 party structure notice: model wording

Use this wording as a guide, replacing everything in square brackets. One notice per adjoining owner.

Party Wall etc. Act 1996: Party Structure Notice (section 3)

To: [full name of each owner] of [address of adjoining property] (the Adjoining Owner)

From: [your full name(s)] of [your address] (the Building Owner)

I/We, the Building Owner, as owner of [address of your property], which adjoins your property known as [address], give you notice that, after the expiry of two months from the service of this notice, I/we intend to carry out the following work to the party wall/party structure between our properties under section 2(2) of the Act:

[for example: (a) section 2(2)(f): cut into the party wall to take the bearings of new steel beams at loft level; (b) section 2(2)(a): raise the party wall to form the new gable.]

[If applicable: The work includes special foundations, details of which are shown on the attached drawings numbered ...]

It is intended that the work will begin on or after [date at least two months after service].

[Optional: I/We propose that [surveyor's name and address] acts as the Agreed Surveyor.]

Signed: [Building Owner(s)] Date: [date of service]

Section 6 excavation notice: model wording

Party Wall etc. Act 1996: Notice of Adjacent Excavation (section 6)

To: [each Adjoining Owner] of [address]. From: [Building Owner] of [address].

I/We give you notice that, after one month from the service of this notice, I/we intend to [build/erect] [description, for example a single-storey rear extension] at [your property] and that, for this purpose, I/we intend to excavate [within 3 metres of your building to a depth lower than the bottom of its foundations / within 6 metres of your building to a depth that meets a line drawn downwards at 45 degrees from the bottom of its foundations]. The accompanying drawings numbered [...] show the site and depth of the excavation and the site of the proposed building.

I/We [do / do not] propose to underpin or otherwise strengthen or safeguard the foundations of your building.

It is intended that the work will begin on or after [date at least one month after service].

Signed: [Building Owner(s)] Date: [date]

Section 1 line of junction notice: model wording

Party Wall etc. Act 1996: Line of Junction Notice (section 1)

To: [each Adjoining Owner]. From: [Building Owner].

I/We give you notice that, after one month from the service of this notice, I/we intend to build a [party wall / party fence wall] [astride the line of junction / wholly on my/our land along the line of junction] between our properties, as described below: [description of the wall, materials, height and length]. [If applicable: The foundations will project under your land, as shown on drawing ...] It is intended that the work will begin on or after [date].

Signed: [Building Owner(s)] Date: [date]

The reply form to send with every notice

Include a reply form the neighbour can sign and return. It should offer three choices:

  1. I/We consent to the works described in the notice.
  2. I/We dissent and concur in the appointment of [your proposed surveyor] as the Agreed Surveyor.
  3. I/We dissent and appoint [name and address] as my/our surveyor.

Remind them that, for a section 3 or section 6 notice, if they do not reply within 14 days a dispute is deemed to have arisen.

Before you use any template

For a version filled in for your project, use our notice generator. If you are unsure which section applies, start with our notice checker.