PartyWallAgreement.org.uk

Schedule of Condition: Why You Need One Before Building

A schedule of condition is a written and photographic record of the neighbouring property before building work starts. You need one because, without it, nobody can prove later whether cracks or damage were there before. It protects the building owner from false claims and the neighbour from unrecorded damage.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

What it is

It records the relevant rooms and structure: walls, ceilings, floors, the party wall itself, cracks, stains and finishes. It uses notes and dated photographs, often with measurements of existing cracks.

Why it matters to the building owner

If a neighbour later says your work cracked a ceiling, the schedule shows what the ceiling looked like before. Without it, you may be paying for damage that was already there.

Why it matters to the neighbour

It lets you show what the property looked like, so new damage is clear. It is your evidence if a claim goes wrong.

How it is agreed

It is usually agreed by the surveyors and made part of the award. Both owners should have a copy. Some surveyors ask owners to sign each page or the last page.

Scope

The extent depends on the work. For an extension, it might cover the shared wall and rooms on the other side of it. For excavation, it might include the whole neighbouring building, including outside walls and paths.

What to keep

Keep your copy of the schedule with the award and your other property papers. If the property is sold, the buyer or their solicitor may ask for it. Take your own photographs of the party wall shortly before work, and store the original files somewhere safe.

Frequently asked questions

Who pays for it?

Usually the building owner, as part of the reasonable costs of the process, as the award decides.

Can I do it myself?

You can take photographs, but a professional record is stronger evidence. Do both if you can.

What if the neighbour refuses to sign?

See the advice on refusal. The surveyors can still record what they see and note the refusal.

How long should I keep it?

Keep it at least until the work is complete, any damage is resolved and the period for a claim has passed. Ask a solicitor if unsure.

Source: Party Wall etc. Act 1996 on legislation.gov.uk

Related guides

Last updated: . This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.

What a good schedule of condition contains

A schedule of condition is a dated record of the neighbour's property, usually prepared by the surveyor before work starts and annexed to the party wall award. A useful one includes:

Crack widths: the scale surveyors use

Many surveyors describe cracks using the damage categories in Building Research Establishment Digest 251, which run from category 0 (hairline cracks under about 0.1 mm) through category 1 (fine cracks up to about 1 mm, easily treated with decoration) and category 2 (cracks up to about 5 mm, easily filled) to more serious categories needing structural repair. Recording crack widths in these terms makes before-and-after comparison much more objective than words such as "slight" or "minor".

The closing inspection

When the work is finished, the surveyor or surveyors should revisit the property and compare it with the schedule. New cracks or widened cracks are listed, and the award usually provides for the building owner either to make good or to pay compensation instead, under section 7 of the Act. If you are the neighbour, ask for this inspection in writing as soon as the builder leaves: memories fade and decorations change.

Without an award

If your neighbour consents to the notice, there is no award and so no schedule annexed to one. You can still agree a schedule informally. Even a set of dated photographs, emailed to both owners before work starts, is far better than nothing if damage appears later.

Typical cost

Schedules are usually included in the award fee. Where one is commissioned on its own, see our guide to the average schedule of condition cost, and our example schedule to see the level of detail to expect.

Download the Party Wall etc. Act 1996 free

Get the full, up-to-date text of the Act as a PDF from the official legislation.gov.uk record, with our plain-English guide to every section, sent straight to your inbox.

We use your email to send the Act. See our privacy notice.

Contact us

Send us a message and we'll reply by email.

We only use your details to reply to you. A quick human check runs when you send.