Party wall notice for a rear extension
A rear extension usually needs a party wall notice if its foundations are within 3 metres of a neighbour's building and deeper than theirs (section 6), if you build a new wall on the boundary (section 1), or if you cut into or build off the existing party wall (section 3). A single-storey extension well away from the boundary on shallow footings may need none.
The three ways a rear extension triggers the Act
| What your extension does | Section | Notice period |
|---|---|---|
| New wall built on the line of junction (boundary), either wholly on your land or astride it | 1 | 1 month |
| Building onto, cutting into, raising or underpinning the existing party wall, or the shared garden wall | 3 (rights in section 2) | 2 months |
| Foundations within 3 metres of the neighbour's building and deeper than its foundations | 6(1) | 1 month |
| Foundations within 6 metres that cut a 45-degree line down from the neighbour's foundations | 6(2) | 1 month, with plans and sections |
By house type
Terraced house
A rear extension on a terrace almost always sits close to both neighbours. Expect a section 6 notice to each, because the new trench foundations are usually deeper than Victorian footings next door. If the extension builds off or cuts into the rear section of the party wall, or the wall is extended along the boundary, add section 3 and section 1 notices.
Semi-detached house
On the attached side the position is the same as a terrace. On the detached side, a side or rear extension within 3 metres of the neighbour's house with deeper foundations needs a section 6 notice.
Detached house
Often no notice is needed at all. It depends on the distance to the neighbour's building and how deep your foundations go. Our guide to party wall rules for detached houses shows how to measure.
How to measure the 3 and 6 metre tests
- Measure horizontally from the nearest part of your new excavation to the nearest part of the neighbour's building or structure.
- Find, or estimate with your engineer, the depth of the neighbour's foundations. Trial pits are often dug for this.
- Within 3 metres: if your excavation will go lower than the bottom of their foundations, section 6(1) applies.
- Within 6 metres: draw a line down at 45 degrees from the bottom of their foundations towards your site. If your excavation will meet that line, section 6(2) applies.
Remember that the neighbour's "structure" includes outbuildings and garden walls, not just the house.
Wall on the boundary: wholly on your land or astride?
A wall astride the boundary needs your neighbour's written consent. If they do not consent within 14 days, you may build wholly on your own land, and section 1 lets you place projecting footings under their land where necessary, subject to compensation for any damage. Building wholly on your own land avoids a shared structure but loses a few centimetres of internal width.
Timing: fit the notices around planning and your builder
Serve your notices while planning or a lawful development certificate is being processed: the one-month and two-month periods then run in parallel. Work must start within 12 months of a section 3 or section 6 notice. If your neighbour dissents, allow several weeks for an award after the notice period ends.
Costs
National guidance from the HomeOwners Alliance (updated March 2026) puts indicative surveyor costs for an extension at around £1,200 to £1,500 per neighbour with one agreed surveyor, or £2,400 to £3,000 where each owner appoints their own. A terrace extension may need awards with both neighbours. See our cost guide.
What your neighbour can and cannot do
- They cannot stop an extension under the Party Wall Act; they can dissent and have surveyors set out how the work is done safely.
- They can ask for a schedule of condition, protection measures, working hours and security for expenses.
- Planning objections are a separate process with the council.
Related guides
Frequently asked questions
Do I need a party wall notice for a single-storey rear extension?
Often yes on a terrace or semi, because the foundations are close to and deeper than next door's. On a detached house set well away from the boundary, often no.
Do I need notice for a rear extension on piles?
Usually yes: piling near a neighbour is excavation that can fall within section 6, and vibration is a common concern the award will address.
My neighbour already has an extension on the boundary. Can I build against it?
Building against or enclosing upon their wall is section 2 or section 11 territory: you will usually need a section 3 notice, and you may have to pay a share of the wall's cost if you use it.
This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.