Party wall 10-day notice: example letter and next steps
A party wall 10-day notice is a written request, under section 10(4) of the Act, asking a neighbour who is in dispute to appoint a surveyor. If they have not done so within 10 days, you can appoint a surveyor to act for them. Send it only after the 14-day reply period has run out with no consent.
When you need a 10-day notice
The 10-day request is the Act's answer to a silent or stalling neighbour. You need it when all of these are true:
- You served a party structure notice (Section 3) or a notice of adjacent excavation (Section 6).
- 14 days have passed since service without written consent. The neighbour is then treated as dissenting, and a dispute is deemed to have arisen (sections 5 and 6(7)).
- They have not agreed to an agreed surveyor, and have not appointed their own.
It also applies when a neighbour has replied "I dissent" but then does nothing more. It is not needed for a Section 1 notice for a wall astride the boundary where the neighbour stays silent: in that case section 1(4) simply means you build wholly on your own land, at your own expense.
What section 10(4) says
If either party refuses to appoint a surveyor, or neglects to do so for 10 days beginning with the day the other party serves a request, the other party may make the appointment on their behalf. All appointments must be in writing. The text is on legislation.gov.uk (section 10).
The surveyor you appoint for the neighbour is their surveyor, not yours. They must act impartially, look after the neighbour's property in the award and agree a third surveyor with your surveyor. You cannot appoint your own surveyor as theirs.
Example 10-day request letter
Example only. This is original wording; adapt the details in square brackets and keep a copy.
[Your name(s)]
[Your address]
[Date]
To [Adjoining owner's name(s)], [their address]
Party Wall etc. Act 1996: request to appoint a surveyor under section 10(4)
On [date served] I/we served on you a [party structure notice under section 3 / notice under section 6] relating to [short description of work] at [address of the work]. You have not given written consent within 14 days, so a dispute is deemed to have arisen under the Act.
I/We have appointed [name, firm and address] as my/our surveyor. I/We now request that you appoint a surveyor to act for you, or agree to [name] acting as the agreed surveyor, and tell me/us in writing.
If you do not do so within 10 days beginning with the day this request is served on you, I/we may appoint a surveyor on your behalf under section 10(4) of the Act. The building owner normally pays the reasonable costs of the surveyors; the surveyors decide this under section 10(13).
Signed: ______ [each building owner]
How to send it
Serve the 10-day request in the same way as the notice: by hand, by post to the owner's usual or last known address, or by email only if they have agreed to email service. Hand delivery with a dated photo is the clearest proof. Our guide to how to serve a party wall notice covers each method.
Timeline: notice to appointment
| Day | Event |
|---|---|
| Day 1 | Party structure or Section 6 notice served |
| Day 14 | Last day for written consent |
| Day 15 | No consent: dispute deemed. Serve the 10-day request. |
| Day 24 | The 10-day period (counted from the day of service) ends |
| Day 25 onward | If still no appointment, appoint a surveyor for the neighbour in writing |
Count from the actual service date. If in doubt, wait an extra day; an appointment made a day too early can be challenged.
What happens after day 10
- You appoint the neighbour's surveyor in writing. Choose someone independent of you and your builder. Our surveyor directory lists surveyors by area.
- The two surveyors select a third surveyor in writing, as section 10(1)(b) requires. The third only acts if called on.
- The neighbour's surveyor writes to the neighbour to explain their role and arrange access for a schedule of condition. Entry needs at least 14 days' notice under section 8.
- The surveyors make an award and serve it on both owners. Either owner can appeal to the county court within 14 days of service.
If the neighbour refuses access for the condition survey, see what to do if a neighbour refuses access to a party wall surveyor.
The other 10-day rules
Section 10 has several 10-day steps, which are easy to confuse:
- 10(3): if an agreed surveyor refuses, neglects to act for 10 days after a request, dies or becomes incapable, the process starts again.
- 10(7): if one party-appointed surveyor neglects to act effectively for 10 days after a request, the other may act alone (ex parte). In Patel v Peters [2014] EWCA Civ 335 the Court of Appeal held that an effective reply, even a late one, ends that power if the other surveyor has not yet acted. See our note on Patel v Peters.
- 10(8): if the two surveyors fail to select a third within 10 days of a request, the appointing officer can select one.
Frequently asked questions
Can I appoint my own surveyor as the neighbour's surveyor?
No. Section 10(4) lets you appoint a surveyor on their behalf, which means a second, separate surveyor. The two then select a third. The neighbour's surveyor must act impartially.
Who pays the surveyor appointed for a silent neighbour?
The surveyors decide who pays the reasonable costs under section 10(13). Where the work is for the building owner's benefit, that is normally the building owner, including the neighbour's surveyor.
Can the neighbour change the surveyor I appointed for them?
Appointments cannot be rescinded under section 10(2). The neighbour cannot simply swap them, though they can contact their surveyor, raise concerns and, if needed, refer matters to the third surveyor.
Do I need a 10-day notice for a line of junction notice?
Not if the neighbour is silent about a wall astride the boundary: silence means you build on your own land. If a dispute does arise under Section 1, section 10 applies, and the 10-day request can be used.
Can I start work once I have appointed their surveyor?
No. Wait for the award and the end of the notice period. Starting disputed work before an award risks an injunction.
This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.