Party wall agreement template: example reply letters

There is no official "party wall agreement" form, because the agreement is usually either the neighbour's written consent to the notice or a party wall award made by surveyors. What you can template is the reply to a notice: consent, or dissent with a surveyor named. The four example letters below are original wording you can adapt; send your reply within 14 days of the notice being served.

Local Surveyor Match
1,920 listings across England and Wales, nearest first.

What people mean by a "party wall agreement"

The Party Wall etc. Act 1996 never uses the phrase "party wall agreement". In practice people mean one of two documents:

  • A written consent. The adjoining owner (the neighbour receiving the notice) agrees in writing to the work described. No surveyor is needed. This is the cheapest route and suits simple, low-risk work.
  • A party wall award. If the neighbour does not consent, a dispute arises and one agreed surveyor, or two surveyors, settle it by an award under section 10. The award says what work can be done, how and when, and who pays. You cannot write an award yourself from a template; only appointed surveyors can make one.

So a "template" is really a reply letter. The building owner's notice is a different document; for that, use our free party wall notice templates or the party wall notice generator.

Before you use any of these letters

  1. Check the date. You have 14 days from the day the notice was served to consent. For a Section 3 (party structure) or Section 6 (excavation) notice, silence after 14 days counts as dissent (sections 5 and 6(7)). For a Section 1 notice about a new wall astride the boundary, silence simply means the wall must be built wholly on your neighbour's land (section 1(4)).
  2. Check which notice you have. The notice should say which section it is served under. Reply to each notice separately if you have more than one.
  3. Check every owner signs. If your home has joint owners, all of them should sign the reply.
  4. Keep proof. Keep a copy and a record of how and when you sent it. Only reply by email if you know your neighbour has agreed to receive notices that way.

If you are unsure which option suits you, read I have received a party wall notice first.

Which letter do you need?

Your situationLetterSurveyor involved?
Small, simple work; you trust the builder; you accept the risk of having no awardLetter A: consentNo
You are happy with the work but want your home recorded firstLetter B: consent with a condition recordNo (a surveyor may still do the record, by agreement)
You want an award but are happy to share one impartial surveyorLetter C: dissent, agreed surveyorYes, one
You want your own surveyorLetter D: dissent, own surveyorYes, two (plus a third selected)

Letter A: consent (example)

Example only. Adapt the details in square brackets.

[Your name(s)]
[Your address]
[Date]

To [Building owner's name(s)], [address]

Party Wall etc. Act 1996: notice dated [date] under section [1 / 3 / 6] relating to [address of the work]

I/We, being the owner(s) of [your address], acknowledge receipt of your notice dated [date] describing [short description, e.g. "inserting steel beams into the party wall for a loft conversion"]. I/We consent to the work described in the notice and its enclosed drawings [drawing numbers]. This consent covers only the work described. If the work changes, please serve a fresh notice.

Signed: ______ [each owner]

Letter B: consent with a condition record (example)

Example only. Use Letter A's heading, then:

I/We consent to the work described in your notice dated [date], on the basis that before work starts a written and photographic record of the condition of [your address], focused on the rooms and walls next to the work, is made and a copy is given to me/us. Please contact me/us to arrange a date. This consent covers only the work described.

Signed: ______

A condition record is not an award, and it does not give you the Act's dispute process unless a dispute later arises. It does give you evidence if damage appears. See why a schedule of condition matters.

Letter C: dissent and agree one surveyor (example)

Example only. Use Letter A's heading, then:

I/We do not consent to the work described in your notice dated [date], and a dispute has therefore arisen under section 10 of the Act. I/We agree to the appointment of [surveyor's name and firm, usually the one named in your notice] as the agreed surveyor under section 10(1)(a).

Signed: ______

Dissent here is not hostile. It is simply the step that brings in a surveyor, a schedule of condition and an award, normally at the building owner's cost.

Letter D: dissent and appoint your own surveyor (example)

Example only. Use Letter A's heading, then:

I/We do not consent to the work described in your notice dated [date], and a dispute has therefore arisen under section 10. I/We appoint [surveyor's name, firm and address] as my/our surveyor under section 10(1)(b). Please ask your surveyor to contact them.

Signed: ______

The surveyor will usually ask you to sign their own appointment letter as well. Appointments must be in writing and cannot be rescinded once made (section 10(2)), so choose carefully. Our guide on how to choose a party wall surveyor lists what to check.

Can neighbours write their own full agreement instead?

Yes. Owners can agree terms between themselves at any stage, and the GOV.UK booklet says agreements should always be in writing. A home-made agreement might record the work, working hours, access, a condition record and who pays for what. Three cautions:

  • A private agreement is a contract, not an award. If it goes wrong, the remedy is the ordinary courts, not the Act's quick appeal route.
  • Wording matters. If the agreement replaces the Act's procedure, you may lose the protections it gives, such as the surveyors' power to deal with damage.
  • A text message or a chat over the fence is weak evidence. See whether a text counts as consent.

Official example letters

The government publishes its own example letters alongside the explanatory booklet, including acknowledgements of line of junction and 3 or 6 metre notices. You can find them on the GOV.UK Party Wall etc. Act 1996 guidance page. The time limits are set by the Act itself, which you can read on legislation.gov.uk (section 10).

Frequently asked questions

Is there an official party wall agreement form?

No. The Act sets out what a notice must contain and how disputes are settled, but it prescribes no form for a reply or an agreement. Any clear written reply that identifies the notice, says whether you consent, and is signed by all owners will do.

Can I consent to some of the work and dissent to the rest?

You can say what you are and are not happy with, but any part you do not consent to puts you in dispute, and the surveyors then deal with the matters in dispute. In practice a partial consent usually still leads to surveyors being appointed.

If I consent, can I still claim for damage?

Yes. The building owner must compensate for loss or damage caused by work under the Act (section 7(2)), whether or not you consented. Without an award or condition record, proving what was caused by the work is harder.

Do I pay for the surveyor if I dissent?

Usually not. The surveyors decide who pays the reasonable costs of the award (section 10(13)), and the building owner normally pays where the work is for their benefit. See who pays the party wall surveyor fees.

What if I miss the 14 days?

For Section 3 and 6 notices you are treated as dissenting, and your neighbour can ask you to appoint a surveyor within 10 days. If you still do nothing, they can appoint one for you under section 10(4). It is better to reply and choose.

This page is general information about the Party Wall etc. Act 1996 (England and Wales). It is not legal advice. Every property and dispute is different, so take advice from a party wall surveyor or a solicitor before you act.